On June 4–5, 2015, the UOP tray assembly for the C3 separation column (tag 21C0606) of the Ningbo Foji Project underwent final inspection at the Changsha Boneng Plant. The inspection was attended by Mr. He Guang, representative of the Owner (Ningbo Foji Petrochemical Co., Ltd.), Mr. Xu Xuebin, representative of the engineering contractor (Hualu Engineering & Technology), Mr. Karl Reeves, UOP Project Manager, as well as Mr. Wang Yi, Mr. Zhang Jinghe, and Mr. Zhang Fa from UOP Shanghai. All parties involved in the inspection highly commended Boneng’s quality control. On the day the final inspection was completed, this batch of products was approved for release by UOP following inspection.